PRIMARY HEALTH CENTRES

?

The administration of Primary Health Centres have been brought under the control of the Director of Public Health and Preventive Medicine from the 1st March, 1996. ??????????

?

Details of Primary Health? Centres sanctioned and functioning:

?

1.1

Number of Primary Health Centres? functioning at the end of VI Five Year? Plan i.e. 1984- 85.

436

1.2

Number of Primary Health Centres sanctioned during 1985 - 86:

?

a) By Converting Rural Dispensaries as? Additional Primary Health Centres

195

b) New Additional Primary Health Centres sanctioned

20

1.3

Number of Primary Health Centres sanctioned during 1986-87 :

?

a) By conversion of Non - Taluk Hospital as Community Health Centres (Upgraded Primary Health Centres) :

41

b) Newly sanctioned Additional Primary Health Centres???????????????????????????????????

5

c) Newly sanctioned Primary Health Centre (Tribal) Nammiampattu?????

1

1.4

New Primary Health Centres established in 1987-88 (Additional)

140

1.5

Number of Primary Health Centres (Additional) sanctioned during 1988-89

(*)? By wounding up of Mobile Health Unit in the PHCs and creation? of? Primary Health Centres.

(*)274

1.6

Number of New Additional Primary Health Centres sanctioned during
1988-89.????????????????????? ????????????????

110

1.7

Number of New Additional Primary Health Centres during 1989-90

a) New Primary Health Centres????????????????????????????????????? :? 123?

b) Conversion of Panchayat Union Dispensaries??????????? ???? :??? 41

164

?

?

1.8

Number of New Additional Primary Health Centres during 1990-91 (Conversion of Panchayat Union Dispensaries)???????????????????????????????? ???

43

1.9

Number of New Additional Primary Health Centre sanctioned during 1991-92

(Perugonapalli in Dharmapuri District).????????????????????????????

1

?

Total

1430

?

14 PHCs have been upgraded as? Taluk Hospitals

(-)? ?14

?

Total

1416

1.10

No. of PHCs sanctioned during 1993-94

1

1.11

No. of PHCs sanctioned during 1995-96

1

1.12

No. of PHCs sanctioned during 1996-97????????????????????? ????????????????

a) New Primary Health Centre????????????????????????????????????? :? 1???? ?

b) Conversion of Panchayat Union Dispensaries????????? :? 2

3

?

Total

1421

1.13

PHC Sankarapuram made as Taluk Hospital

(-)???? 1

?

Total

1420

1.14

Conversion of Panchayat Union Dispensaries

?????? 11

?

Total

1431

1.15

23 PHCs have been upgraded as Taluk? Hospital

(-)?? 23

?

Total

1408

1.16

No. of PHCs Sanctioned during 1998-99

???????? 6

?

Total

1414

1.17

5 PHCs have been upgraded as Taluk hospitals/ Non-Taluk Hospitals

(-)???? 5

?

Total

?? 1409

1.18

No. of PHCs upgraded as Taluk Hospitals

(-)?? 12

?

Total

?? 1397

1.19

No. of PHCs sanctioned during 99-2000

???????? 2

?

?TOTAL

?? 1399

1.20

No. PHCs sanctioned during 2000-2001

12

1.21

Upgradation of PHC Kurinjipadi, Cuddalore Dist. as Non Taluk Hospital

(-)???? 1

?

TOTAL

1410

1.22

No. of PHC sanctioned during 2001-2002

1

?

TOTAL

1411

?

Community Health Centres / Upgraded Primary Health Centres sanctioned and established:

No. of Upgraded PHCs

?????? 24

No. of Non-Taluk Hospitals converted as Community Health Centres 1986-87

?????? 35

Total

?????? 59

No. of? PHCs upgraded during 2001-2002 (upto 28.02.2002)

21

TOTAL

80

No. of PHCs upgraded during 2002-2003

37

Total

117

Existing staff pattern for Main Block Primary Health Centres:

1.

Medical Officer

2

2.

Pharmacist

1

3.

Auxiliary Nurse Midwife

1

4.

Male Nursing Assistant

1

5.

Junior Assistant

1

6.

Driver

1

7.

Cook-cum-Waterman

1

8.

Sweeper

1

9.

Lab. Assistant

1

Additional Staff for Upgraded Primary Health Centres:

?

1.

Medical Officer - Civil Surgeon

1

2.

Medical Officer - (PG Qualified Civil Assistant Surgeon)

1

3.

Staff Nurse

2

4.

Pharmacist

1

5.

Male Nursing Assistant

1

6.

Female Nursing Assistant

1

7.

Sweeper

1

8.

Radiographer

1

9.

Dark Room Assistant

1

10.

Laboratory Technician Grade-II

1

?

Primary Health Centres Building Facilities:

?

1

Total No. of Primary Health Centres

1411

2

Primary Health Centres Functioning in Government buildings

1347

3

Primary Health Centres sanctioned and under construction at various stages

?? 26

4

In Private/Panchayat Union Buildings

?? 38

?

Total

1411

?

Availability of quarters

?406

?

Tribal Welfare Scheme

?

Under this scheme, nine blocks, have been identified as Tribal areas in the State. All these Blocks have one Primary Health Centre. Among the nine Primary Health Centres one Primary Health Centre at Alangayam and Kariyalur has been upgraded.

?

??????????? Adequate preventive, promotive and curative services and all National Health Programmes are being implemented through the network of Primary Health Centre/Health Sub Centre in the Tribal Sub Plan area for the welfare of Tribals.

?

The details of Primary Health Centres and Community Health Centres functioning in Tribal Areas as follows :

?

Old Regular

? 7

Upgraded Primary Health Centres

? 2

Under Tribal Sub-plan scheme

14

Dispersed Tribal Group

?? 1? (Pechiparai in Kanyakumari District)

PHC Uprgraded as Taluk Hospital

?? 1

?

National Scheme for the Prevention of Visual Impairment and Control of Blindness:

?

This scheme is being implemented in Primary Health Centres. The main objectives of the programme are as follows:-

a.

To render treatment for minor eye ailments

b.

To prescribe glasses for the correction of refractive errors

c.

To educate the school children and the rural masses on eye care and prevention of the common causes of blindness.

d.

To conduct Mini eye camps at Main PHCs wherever Operation Theatres are available.

e.

To any other works relating to eye care.

?

384 posts of Ophthalmic Assistants have been sanctioned at the rate of one for each PHC in the block.

?

In-Patients and Out-Patients treated during 2002:

?

Sl.No.

Name of the District

Out-Patient

In-Patient

Daily average

Monthly Average

O.P.

I.P.

1

Coimbatore

2402922

6613

96.81

8.1

2

Cuddalore

2197580

10679

120.42

17.8

3

Dharmapuri

2241513

18263

89

22.06

4

Dindigul

2175526

13782

121.64

23.44

5

Erode

2343802

6781

97.29

8.56

6

Kancheepuram

1885628

7310

109.92

12.96

7

Kanyakumari

1368329

4839

124.96

13.44

8

Karur

1086228

3229

102.62

9.28

9

Madurai

1904514

5827

124.23

11.56

10

Nagapattinam

1394405

3762

88.84

7.29

11

Namakkal

1627485

4799

94.87

8.51

12

The Nilgiris

483808

2320

47.34

6.9

13

Perambalur

1735250

9693

101.15

17.19

14

Pudukkottai

1765168

5710

93

9.15

15

Ramanathapuram

1298048

7179

77.31

13.01

16

Salem

2871974

5816

112.41

6.92

17

Sivaganga

1250501

6017

77.86

11.4

18

Thanjavur

2645171

4568

124.95

6.56

19

Theni

1197001

5745

132.06

19.28

20

Thiruchirappalli

1856166

9073

103.78

15.43

21

Thirunelveli

2654505

2925

117.3

3.93

22

Thiruvallur

1644930

4444

109.92

9.03

23

Thiruvannamalai

2497759

15177

85.54

15.81

24

Thiruvarur

1540772

7623

108.24

16.29

25

Thoothukudi

1554530

1549

90.62

2.75

26

Vellore

2635453

13217

107.77

16.44

27

Villupuram

1365856

3321

103.95

7.69

28

Virudhunagar

2701564

10877

92.52

11.33

?

Total

52326388

201138

101.61

11.88

?


Objective Classification (PHC Wing):

?

(Rs. In Thousands)

Head of Account

Budget Estimate 2002-2003

Revised Estimate 2002-2003

Non-Plan

Plan

C.S.S

Total

Non-Plan

Plan

C.S.S

Total

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

01. Salaries? ???????

??? 01. Pay

737047

45980

12249

795276

831915

49521

11452

892888

??? 02. Medl.? Allowance

6667

393

106

7166

6959

351

108

7418

??? 03. Medical Charges

40

18

4

62

40

27

2

69

??? 04. Other Allowances

45277

3850

530

49657

28595

3039

41

31675

??? 05. Interim Relief

1

?

2

3

26

?

?

26

??? 06. H.R.A.

32990

2273

569

35832

35465

1804

527

37796

??? 07. Travel Concession

1000

30

15

1045

1010

30

4

1044

??? 08. C.C.A.

1912

234

47

2193

2177

183

33

2393

02. Wages

400

?

?

400

400

?

?

400

03. Dearness Allowance

361153

22530

6002

389685

399354

23770

5497

428621

04. Travelling Expenses

??? 01. Tour T.A.

10000

320

440

10760

10035

335

390

10760

??? 02. Transfer T.A.

400

15

12

427

348

35

8

391

??? 03. F.T.A.

1838

100

?

1938

1020

47

?

1067

05. Office Expenses

?? 01. Telephone Charges

110

1057

?

1167

140

1237

?

1377

? 02. Other Contingencies

5775

1983

7

7765

5550

2166

7

7723

??? 03. Electric Charges

12097

82

?

12179

10000

112

?

10112

0600 Rent Rate Taxes

01 Rent

650

?

?

650

150

?

?

150

02 Property Tax

25

?

?

25

50

?

?

50

03 Water Charges

85

?

?

85

75

?

?

75

08. Advertisement & Pub

45

?

?

45

45

1000

?

1045


(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

0801 Grants in aid

?

1

?

1

?

1

?

1

1900 Machinery & Equipments

01. Purchase

?

1

1

2

?

54367

1

54368

03 Maintenance

100

300

?

400

10

300

?

310

21. Motor Vehicle

??? 01. Purchase

?

1

?

1

?

10500

?

10500

??? 02. Maintenance

1000

71

?

1071

1000

71

?

1071

24. Materials and Supply

?

1500

?

1500

?

554

?

554

2500 Interest

?

?

?

?

?

?

2

2

33. P.P.S.S.

20

?

?

20

15

?

?

15

45. P.O.L.

6000

690

?

6690

6000

776

?

6776

46. C.T.S.

215

70

?

285

190

70

?

260

47. S & E

185

510

?

695

185

5102

?

5287

49. F.A.

11288

692

202

12182

11288

692

179

12159

51. Compensation

1

?

?

1

605

?

?

605

10. Prizes & Awards

125

2

?

127

44

2

?

46

66. Medicines

113963

49624

1

163588

118963

38788

1

157752

67. F.D.C.

1200

15

?

1215

1000

15

?

1015

72. Training

100

?

?

100

49

?

?

49

73. Transport Charges

300

17

1

318

300

17

1

318

77. Deduct Recoveries

-11288

-692

-202

-12182

-11288

-692

-179

-12159

Total

1340721

131667

19986

1492374

1461715

194220

18074

1674009

Charged

-1

?

?

-1

-605

?

?

-605

TOTAL

1340720

131667

19986

1492373

1461110

194220

18074

1673404

?


Construction of HSCs under NABARD & PMY

?

I

Contraction of 100 HSCs under PMGY Scheme during the year 2000-2001 vide G.O.Ms.No.245, Health dated 14.09.2001.

?

??? 100

ii

Construction of 100 HSCs availing NABARD loan under RIDF VII during the year 2002-2003 vide G.O.Ms.No.95, Health dated 31.05.2002

?

??? 100

?

iii

Construction of 100 HSCs availing NABARD? loan under RIDF VII? during the year 2002-2003 vide G.O.Ms.No.96 Health dated 31.05.2002

?

??? 100

iv

Construction of 100 HSCs availing NABARD? loan under RIDF VIII? during the year 2002-2003 vide G.O.Ms.No142 Health dated 31.05.2002

?

98

?

?

Total Construction of HSC

??? 398

?

Out of 398 Health Sub Centres, Public Works Department Authorities have undertaken work for 384 Health Sub Centres.

?

?

?